Loudoun supervisors paused votes on data center and substation rezonings for up to 12 months. The pause could affect 33 active applications and ends when new rules are adopted.
The Loudoun County Board of Supervisors has paused its votes on data center and electrical substation applications for up to 12 months. That is the longest pause Virginia law allows.
A majority of the board voted for the pause at its meeting Tuesday, Nov. 17, the county said in a news release on Nov. 18. The board made it retroactive to Sept. 15.
The pause could affect 33 legislative applications that are active now, the county said.
Why the board paused
The county is rewriting its rules on where data centers can go and how they must be built. That work is the Data Center Standards and Locations project. It would change the county’s 2019 Comprehensive Plan and its Zoning Ordinance.
Those changes could affect applications already in the system, the county said. The project is expected to wrap up in summer 2027. The pause ends when the board adopts the new plan and zoning amendments.
An earlier legal opinion from the county attorney found that a moratorium stopping all data center approvals would not be legal, the release said. A pause on board votes is the narrower step the board took instead.
What the pause does and does not do
Under the resolution, the board’s final votes on these applications are put off for up to a year. The year starts when an application is first submitted to the Planning Commission.
During the pause:
- developers can still file applications for data centers and substations
- county staff will keep reviewing them
- the Planning Commission will still hold its public hearings
- the board will not hold its own public hearings or votes on them until the standards project is done
- no application becomes inactive because of the pause
The board may make exceptions. The county named two: applications that involve the reliability of the electric grid, and applications whose legal deadline for a decision is about to run out.
The pause does not cover:
- properties in the Route 28 Tax District
- applications that go through administrative review instead of a board vote
The board had already ended by-right data center development. Every data center project now needs a board vote through the county’s special exception process, the county said.
How this fits with this fall’s other data center moves
The pause comes weeks after the county began requiring noise studies and substation details with data center rezoning applications. It is separate from the board’s preliminary deal with Amazon to keep data centers off the former George Washington University campus in Ashburn.
What it means for you
- A data center case near you may stall at the board. If a data center or substation application is pending near your neighborhood, it can still reach a Planning Commission hearing, but the board is unlikely to vote on it until the new standards are adopted.
- The bigger fight is the new rules. Where data centers may go in the future will be set by the standards project. Its updates and comment opportunities are posted on the county’s project page.
- Read the resolution. The adopted resolution is attached to item 14.m of the Nov. 17 board agenda. The county also keeps a data centers page and a transmission lines page.
- Follow a case. How zoning applications work in Loudoun, and how to comment on one, is on our building permits and zoning page.
Have your say